September delivered two genuine milestones for EasyProperties investors: Tungsten's units were lodged for transfer at the Pretoria Deeds Office, and Saxon Square was granted occupation following desnagging — alongside steady construction progress across the remaining seven sites. Full status update below.

The Tungsten

We're delighted to confirm that the Tungsten units were successfully lodged for transfer at the Pretoria Deeds Office this month. The documents will now go through the examiners' review process at the Deeds Office, following which the development and transfer will be registered. Transfer is expected to take place within September. We look forward to updating you once registration is confirmed.

Saxon Square

Occupation of the units has been granted following completion of the desnagging process, and focus has now shifted to securing tenancy for the 5 units. On the registration front, the transferring attorneys have confirmed that two outstanding items remain: the Section 53 certificate (the City of Johannesburg's consent to open the sectional title register) and the rates clearance figures for the land on which the scheme is established. The developer is actively managing both municipal processes and remains hopeful of registration by the end of September 2026.


2 on Hill

Work is progressing on the last level of the superstructure, with brickwork on the walls and roof underway. The next steps involve sealing the building with windows and doors, followed by tiling, flooring, and internal finishes such as cupboards. The project remains targeted for completion within 2026; however, the main contractor has submitted a time extension application due to severe weather experienced during construction, which, if granted, could move completion into the first quarter of 2027. We'll keep you updated as this progresses.


Vanderbilt

Construction continues to progress well: the façade is taking shape with windows and doors 95% complete, drywalling and ceilings finished, and internal wet works and floor tiling well underway. Apartment doors, kitchens, cupboards, and granite countertops are being installed, alongside final bathroom fittings, while the hot-water plant has been delivered to the roof and is being connected. With the development on track for completion in Q4 2026, we look forward to keeping you updated as Vanderbilt nears the finish line.

Woodstock Quarter

Registration continues to be managed by the appointed attorneys and remains in progress. The transferring attorneys are still awaiting the outstanding guarantees from the bond attorneys and the bank before the process can move forward, and we are aggressively following up to expedite this. Although registration had initially been expected in early August, this timeline has since shifted, and updates will be given once a solid timeline has been provided.

The Hive

Construction is progressing well: brickwork rose from the slab in July 2026, and by August 2026 all structures reached full roof height. This marks a major milestone, with buildings now fully elevated from the ground up. Occupation remains estimated for Q1 2027.

 

164 Eccleston

Transfer rates applications are currently in progress, and Transfer Duty Receipts have been requested from SARS. Documentation and payments are largely complete across two portions, with one outstanding matter still being followed up. Lodgment is expected by the end of September 2026, with registration to follow. We'll keep you updated as we move closer to registration. Construction will then begin onsite. EasyProperties investors will be paid the capital plus interest on the first portion of the investment on transfer of the first two stands. The 2nd part of the investment will be paid on the transfer of the 3rd and 4th stand.

We'll keep you updated as we move closer to registration.

One on Anne

We've got an update from our conveyancer, Calteaux & Partners, but it's not quite lodgement time yet. A few things are still in the queue: A rates clearance from council, the Surveyor General's electrical servitude diagram, and SARS's decision on the transfer duty exemption certificate. The builder's NHBRC certificate also still needs to reach the bond attorneys.

Once these outstanding items are finalised, we will receive an updated lodgement date from the conveyancers. We will continue to update as we receive more information.

Monarch Development

This month's construction update for The Monarch: column works supporting the transfer slab on Block C are complete, with casting now underway on Blocks A and B to continue structural advancement. Stair and lift bases are fully cast, with their walls progressing alongside the surrounding structure. Decking and steel fixing for the transfer slab are progressing on programme — this slab forms the ground floor of Block C and the parking level for Blocks A and B, which sit further back on the site. Ground preparation and paving are progressing in the basement parking area alongside the structural works above. Looking ahead, the team will be casting further sections of the transfer slab, progressing Block C to its second storey, continuing work on the stair and lift cores, and carrying on with paving and layer works in the parking area. More updates will follow as we receive them.

 